MYKOLAIVOBLENERGO JSC

Reconstruction of 150/35/10 kV substation SNIGURIVKA for the purpose of connecting two solar power plants with a capacity of 15 MW and 47 MW.

Replacement of two 150/35/10 kV 1-T and 2-T power transformers with new ones with a capacity of 63 MVA each

Replacement of circuit breakers, disconnectors and current transformers in the input cells of 1-T and 2-T transformers at the open 150 kV switchgear

Replacement of circuit breakers, disconnectors and current transformers in the input cells of 1-T and 2-T transformers at the open 35 kV switchgear

Replacement of circuit breakers, disconnectors and current transformers in the input cells of 1-T and 2-T transformers in a closed 10 kV switchgear

Installation of a 35 KV outdoor switchgear

Manufacturing and installation of relay protection and automation panels

Installation of high frequency communication equipment

Reconstruction and adjustment of telemechanics systems

Commissioning works